3 June 2002
Mowlem Marine has announced that the project is behind schedule and will probably overrun the completion date. The new ferry service run by Northlink is due to start on 1 October 2002 when it had been hoped the new Pier would be ready. Various problems including bad weather have held up progress at the site. Scrabster Harbour Trust and Consultants Babtie Group are pressing the contractors to push ahead. The scheme is part funded by the Scottish Executive and European Regional Development Fund |